24 August 2015

This week at Upper Hunter Tertiary Education Centre

The following work is planned for this week:

  • Complete lightweight framing to level 2;
  • Commence cladding;
  • Continue roofing and soffit linings;
  • Pour level 1 to level 2 stair flights to stair 1 and 2;
  • Pour plant room slab, tank room slab;
  • Continue brickwork to underside of level 1 soffit lining, continue brickwork to western elevation; and
  • Continue services rough in to level 1 internally.

This week at Campbell's Corner

Works for this week include: 

New Building

•         Structural Steel to first floor and then ground floor. Crane and delivery trucks will affect the carpark. Contractor to control movements to cause as little disruption to car park, general public and tenants:

•         Services rough-ins to new bathroom area;

Refurbishment Works

•         Scaffold Installation over Bridge Street shops;  

•         Painting to 1st floor exterior;

•         Timber window refurbishment;

•         Wall and ceiling linings continuing;

•         Services rough-ins continuing; and

•         Ground floor rough-ins commencing.

17 August 2015

This week at Campbell's Corner

Works for this week include:

Ground Floor

  • Structural steel installation. Please note there will be minor disruption to the carpark Mon – Wed for cranes and delivery of steel;
  • Blockwork to front stairs;
  • Demolition works to front of IGA. These works will be performed at night to limit disruption to IGA and general public;
  • Fire rated ceilings continuing;

First Floor

  • Wall linings continuing;
  • Structural steel installation;
  • Services rough-ins continuing

Exterior

  • Wall preparation and painting to the first floor; and
  • Awning works commencing on Brook St.

 

This week at The Upper Hunter Tertiary Education Centre

The following work is planned for this week:

  • Commence safety mesh and roof sheeting;
  • Continue lightweight steel framing to level 1;
  • Pour stair 1 and 2, from ground to level 1;
  • Form level 1 to level 2 flights to stair 1 and 2;
  • Install windows to level 1;
  • Continue bricklaying on ground floor, moving up to level 1; and
  • Prepare lower ground floor slabs to plant room, store room, lift and stair lobby as well as spoon drains.

5th August 2015

This week at Campbell's Corner

  • Precast Panel installation this Thursday 6 August and Friday 7 August – expect significant disruption to the rear carpark and parking bays to Brook Street. There will be cranes and trucks in this area to be able to complete the works;
  • There are 29 panels to install, 26 which will be installed from the Campbell’s Corner Carpark and 3 from Brook Street. The 26 will be done first;
  • Parking bays in Brook Street for parking trucks for delivery of panels as well as closing off a section of the carpark area to keep the general public safe from the heavy machinery;
  • We are attempting to have this completed all on the Thursday but there may be a run over into the Friday; and
  • Traffic Control signage and controllers will be in place for the entire two days.

 

10th August 2015

This week at Upper Hunter Tertiary Education Facility

The following work is planned for this week:

  • Crane all gyprock for level 1 and level 2 floors up on Wednesday morning at 7:00am;
  • Commence lightweight steel framing to level 1 perimeter walls, and internal walls;
  • Measure up for roof sheets to all levels;
  • Continue rough in to A/C, hydraulic and electrical;
  • Continue brickwork from ground floor (GF) to level 1;
  • Pour stair 1 and stair 2 from LGF to GF.

This week at Campbell's Corner:

Works for this week include:

Ground Floor

  • Structural steel installation;
  • Services rough ins;
  • Blockwork to stairwell and walls;
  • New temporary entry to bridge street entry; and
  • Demolition works to front of IGA. This will be done at night time.

First Floor

  • Structural steel installation;
  • Linings installation to continue; and
  • Services rough in to Atherston Room.

Structural steel installation will comprise of a crane working in the construction area with deliveries of steel. This will commence on Wednesday. Expect truck delivers for the remainder of the week.

This will cause only minor disruption to the carpark.

27 July 2015

This week at the Upper Hunter Tertiary Education Centre

The following work is planned for this week:

  • Commence structural steel to level 1 and level 2 slabs, crane to be set up within site at either the existing Loxton House car park location or in the south west corner of the site adjacent to the library;
  • Continue perimeter lightweight steel framing to ground floor, moving onto internal wall framing once perimeter framing stood;
  • Suspended drainage works for cleaners room and amenities on level 1 and level 2;
  • Continue laying bricks to the ground floor level, moving onto blocks on lower ground level if inclement weather is affecting site; and
  • Continue loading out the last of the formwork which has been stripped from the ground and lower ground levels.

This week at Campbell's Corner

Works for this week include:

Ground Floor

  • Blockwork to stairs at foyer entry and rear wall;
  • Fire rated ceiling works;
  • Services rough ins;

 1st Floor New Building

  • Pouring concrete floor on Tuesday, expect concrete pumps and trucks using the carpark area;
  • Blockwork to lift Shaft to commence;

 1st Floor Existing Building

  • Steel work to termite repairs;
  • Services rough ins continuing;
  • Linings to walls;

 External

  • Scaffold completed to awning area; and
  • Cleaning and preparation of existing 1st floor façade.