20th July 2015

This week at Campbell's Corner

Works for this week include:

Ground Floor

  • Scaffolding starts to the awning area. Frequent truck deliveries Monday to Wednesday. Scaffold items will be temporarily stacked on Brook Street footpath for use;
  • Blockwork to stairs and walls;

1st Floor

  • Steel reinforcement to first floor slab;
  • Concrete pour scheduled for Friday. Expect concrete trucks and pumps onsite using part of the carpark as previous pours;
  • Plasterboard linings to one side of walls;
  • Services rough-ins continuing; and
  • Window refurbishment continuing.

This week at the Upper Hunter Tertiary Education Centre

The following work is planned for this week:

  • Complete block work to lift shaft walls;
  • Core fill western stair walls and lift shaft walls Tuesday afternoon (boom pump on site but all works contained within site);
  • Commence concrete roof slabs to stair 1 and stair 2, anticipate to pour both lids on Thursday;
  • Stripping to continuing of formwork from level 2, then Level 1, ground floor and finally lower ground floor;
  • Completion of internal stud work to allow bricklaying to external skin on northern and western elevations to ground floor; and
  • Final scaffold lift to stair 2 on Monday.

We are also looking to bring in a crane on Wednesday to lift down all formwork from level 2 and level 1. This will not affect traffic flow around the site, as all works will be contained within the site fencing.

13 July 2015

This week at Campbell's Corner

Works for this week include:

Exterior

  • Scaffold to awning mid-week. It was scheduled for last week but the builders are awaiting a further delivery. When erected the scaffolding will take up space on the footpath but ample pedestrian and shop access will remain;

Ground Floor

  • Formwork continuing for first floor slab;
  • Blockwork to foyer stairs;
  • Fire Rated Plasterboard installation;

First Floor

  • Atherston Room Truss Works;
  • Services installation – Mechanical & Fire;
  • Timber Window Refurbishments; and
  • Plasterboard Linings.

This week at Upper Hunter Tertiary Education Centre

The following work is planned for this week:

  • Continue block work to top of lift shaft/stair 1/stair 2;
  • Commence stripping formwork from level 2 and continue stripping down to ground floor;
  • Commence lightweight steel framing to ground floor; and
  • Erect the final lift of scaffolding to form catch deck for future roofing works.

It is scheduled for a crane to be onsite from 7:00am Tuesday morning to lift scaffolding, blocks and sand/cement for mortar and ancillary items. This is not expected to affect traffic conditions outside the site.

15 June 2015

This week at Campbell's Corner

Works for this week include:

  • Blockwork to ground floor. Expect concrete trucks and pump Wednesday for grouting of blocks;
  • Formwork to commence Wednesday;
  • Concrete works to new front foyer and Greater area. Expect concrete trucks and pump Friday;
  • First floor walls and ceiling framing to continue;
  • Services rough in to first floor to continue; and
  • Pump House hydraulic works to continue.

 

This week at the Upper Hunter Tertiary Education Centre:

The following work is planned for this week:

  • Continue tying steel to Level 1; 
  • Form up columns in preparation of pour of Level 1 (at this point, scheduled for Monday 22 June); and
  • Pour piers to upper forecourt area for structural steel connection.

A crane is booked for 7:00am Wednesday morning to lift the top mat of steel reinforcing to Level 1, which will be on site at 8:00am. The lifting of steel will be straight off the truck onto the deck.

22 June 2015

This week at Campbell's Corner

Works for this week include:

  • Concrete works to ground floor front tenancies. Expect reinforcement deliveries, concrete trucks and pumps throughout this week;
  • Formwork commencing today for first floor slab;
  • First floor services installation continuing;
  • Scaffold to awning (subject to Section 138);
  • Window and door refurbishments to first floor;
  • Ceiling framing to first floor continuing; and
  • Fire rated ceilings to ground floor to commence

 

This Week at Upper Hunter Tertiary Education Centre

The following work is planned for this week:

  • Complete tying steel to Level 1;
  • The concrete pour for Level 1 will start early Tuesday morning and finish approximately 2.00pm followed by concrete finishers surfacing the concrete for up to 8 hours depending on concrete curing;
  • During the pour period, there will be minor disruptions to local traffic in Hill St and towards the library precinct and traffic control will be in place;
  • On Wednesday a 55t crane will be on site from 7:00am lifting blocks, formwork and scaffolding onto Level 1 to commence work for Level 2.

9 June 2015

This week at Campbell's Corner

While tenants of Campbell’s Corner will be communicated with frequently about the works the intention of this update is to keep neighbouring businesses and community informed on works scheduled for the week ahead.   

Works for this week include:

Ground Floor

  • Blockwork to ground floor area;
  • Concrete trucks and pump for core filling on Wednesday; and
  • Demolition of internal ceilings.

First Floor

  • Walls and Ceiling framing;
  • Services rough in continuing; and
  • Floor cement sheeting to Atherston Room

This week at Tertiary Education Centre:

The following work is planned for this week:

  • Commence tying steel to the beams on level 1, followed by the bottom mat of steel in the slab sections;
  • Formwork to finish off the formwork tables in the slab sections, followed by edge boards;
  • Core filling to block work; and
  • Excavation and placement of road base to upper forecourt area. 

There will be another steel delivery later in the week (likely Friday) and another crane visit on site for this delivery. Apart from the steel delivery there are no other disturbances outside the site expected.