11 January 2016

This week at Upper Hunter Tertiary Education Campus

The following work planned this week:

  • Landscaping;
  • Painting;
  • Final roofing works; and
  • Air-conditioning.

This week at Campbell's Corner Refurbishment

Works for this week include:

On Wednesday is the installation of the awning columns along Bridge St. One road lane will be closed to allow the use of a Hiab truck. Traffic control will be in place from 9.30am to 3.00pm.

On Thursday this work will continue along Brook St.

Ground Floor

  • Toilet fixtures installation continuing; and
  • Tiling continuing including entrances.

1st Floor

  • Painting continuing;
  • Air-conditioning continuing;
  • Electrical rough-in continuing; and
  • Carpet is being laid.

External

  • Painting to external facades continuing.

4th January 2016

This week at Campbell's Corner

Works for this week include:

Ground Floor

  • Toilet fixtures installation continuing; and
  • Tiling continuing.

1st Floor

  • Painting continuing;
  • Air-conditioning continuing; and
  • Electrical rough-in continuing.

External

  • Painting to external facades continuing. 

Please note a 200 tonne crane will be onsite from 7am for approximately 6 hours installing air-conditioning ducts on roof.

14 December 2015

This week at Upper Hunter Tertiary Education Centre

The following work planned this week:

  • Vinyl laying to ground floor and commencing vinyl to stair/lift lobbies;
  • Electrical, hydraulic fitout;
  • Line marking to car park;
  • Upper forecourt concrete works;
  • Delivery of admin counter, doors to kitchenettes;
  • Form and pour footpaths to perimeter of building; and
  • External cleaning to hard surfaces. 

The western Council car park is NOW open for through traffic and will be available as a public car park by Wednesday 16 December.

 

This week at Campbell's Corner Refurbishment

Works for this week include:

The electrical contractors are coordinating the electrification of the new electrical kiosk and new main switchboard. The majority of impacted businesses are tenants of Campbell’s Corner but all businesses to be potentially impacted have been contacted.

Ground Floor

  • Toilet fixtures installation continuing;
  • Services fitout continuing;
  • Shop fronts continuing;
  • Electrical mains works continuing; and
  • Tiling of ground floor.

1st Floor

  • Ceramic tiling continuing;
  • Carpentry fitout continuing;
  • Painting continuing;
  • Wall linings to new building continuing;

 External

  • Painting to external facades continuing; and
  • Roofing works continuing.

The new entry off Bridge Street is now open. Tiling of this area will commence after Christmas.    

21 December 2015

This week at Campbell's Corner

The electrification of the new electrical kiosk and new main switchboard was successful.

Works for this week include:

Ground Floor

  • Toilet fixtures installation continuing;

1st Floor

  • Painting continuing; and

External

  • Painting to external facades continuing. 

Works will stop over Christmas from Wednesday 23/12/15.

7th December 2015

This week at Campbell's Corner Refurbishment

Works for this week include:

Ground Floor

  • Toilet fixtures installation continuing;
  • Suspended ceiling works continuing;
  • Services fitout continuing;
  • Shop fronts continuing;
  • Electrical mains works continuing;
  • Roof sheeting to awning be installed;

1st Floor

  • Ceramic tiling continuing;
  • Carpentry fitout continuing;
  • Painting continuing;
  • Wall linings to new building continuing;

External

  • Painting to external facades continuing; and
  • Roofing works continuing.

The new entry off Bridge Street is to be open by the end of the week. Tiling of this area will commence after Christmas. 

 

This week at Upper Hunter Tertiary Education Centre

The following work planned this week:

  • Asphalt to car park;
  • Concreted pour of eastern access ramp;
  • Commence concrete to upper forecourt;
  • Continue vinyl works to ground floor;
  • Fit-out to all floors, electrical, hydraulic and mechanical;
  • Cleaning to block work and external areas; and
  • Completion of painting to all floors. 

The western Council car park is to be open for through traffic by Thursday 10 December and available as a public car park by Wednesday 16 December.